What is Earned value management?

A way to measure project progress by comparing planned work, completed work and actual cost.

In plain English

Three numbers drive it: planned value (PV), earned value (EV, the budgeted value of the work actually done) and actual cost (AC). Cost variance is EV minus AC, and schedule variance is EV minus PV. The indexes are CPI = EV / AC and SPI = EV / PV. Above 1 is good, below 1 is a warning.

Example

If you have done work budgeted at $40,000 (EV) but spent $50,000 (AC), CPI is 0.8 and you are over budget.

Where you will meet it

This idea belongs to the subject area of these practice tests. We do not publish or predict real exam questions.

Related terms

  • Critical path: The longest chain of dependent tasks in a project, which sets the shortest possible project duration.
  • Scope creep: Uncontrolled growth in what a project is expected to deliver.

Test yourself

Practice tests with an explanation for every answer option, so each mistake teaches you something.

Browse practice testsAll glossary terms

Written and checked by the Be Ready Education team, last reviewed 2 November 2026. General study information, not professional advice. Providers change names and rules, so confirm details on the official documentation. Not affiliated with, endorsed by or sponsored by any certification vendor or exam body. Certification names, exam codes and product names are trademarks of their respective owners and are used only to identify the exam a practice product prepares for. Our questions are original and are not actual exam questions.